Saturday 28 September 2013

Lock Up

Mostly bricked
We are just reaching lockup now, which isn't as good as it sounds, although it is a milestone in the project. With the lockup stage upon us it means a very big bill (progress payment - 35%) and no ability to see things inside the house, other than through muddy windows.

 The front door has been fitted (to be stained) and the internal doors have been hung.
Front Double door
The brickwork is still dragging out due to weather - the majority of the house is done, with just the higher layers on the alfresco, front and the pillars to be done.


Alfresco - Under construction

The next things scheduled to happen is further carpentry inside, as the skirting boards & architraves fixing has started. Painting is lined up to happen next, along with fitting off of plumbing and eletrical.



No comments:

Post a Comment