Sunday, 15 September 2013

Electrical and plumbing in


 
Switch Box
The nice frame of the house has now been fitted out with the basic plumbing and the electricals of the house (The frame looked nicer without them!). The ducting for the central heating had been installed into the roofspace as well.

Bricks, Plasterboard and door-frame supplies had arrived - all the resources for the next weeks worth of work. We are glad that our choice of bricks was in stock (no need to worry about how alternative bricks will match + additional costs incurred).

Electrical, Data  & plumbing
The electrical work in the place did see the cables go everywhere - making for a big web of cables behind almost every wall. We had elected to go with slimline points, which means all our power and data outlets are attached to wall studs - hoping they look great as a finished product.

Sunday, 1 September 2013

Roof - Complete!

Roof Complete
Our colourbond roof is now complete and looking good. We are happy to see the progress and great to see it all really taking shape.

Side/full view

The next stages are the start of internal plumbing and cables, follow by brickwork. The house should be heading to lockup soon (less photos and information then!).

Inside

Truss, batons & Sarking


Roof - Under construction


Roof under construction
A week after the frame had been done, the gutters went up initially and then our colourbond roof went up, along with the sarking underneath the roofing.

The roof is 25' degree pitch - as required by the estate (added cost for the build) - with the all important safety rail to ensure the workers are safe.

The light colour is looking great and we are happy with our choice. Hopefully with a lighter colour it will absorb slightly less heat then a darker colourbond roof - it will also contrast the darker colour bricks that will be coming soon.

Frame Stage - Complete!

Shell of the house

Our frame stage has now completed, with the trusses installed. They have also tacked on the extra noggins in the locations we requested (excluding bathrooms at current).

It is really taking the shape of a house now and its interesting to see and know the design of the place - hopefully that will make it easier for post hand over works in the future (both short and long term).

We have organised for New Home Inspections to inspect our frame stage and provide us with a written report. We are wanting to ensure that any problems are flagged as soon as possible, rectified in a timely manner and that the building is to code (which we know nothing of - so hiring a professional!).

Next stage is for the gutters & the colourbond roof to be attached. Looking forward to that and pictures to follow for that stage as well.
Right side of house

Internal Framing (Photo's)

Just a collection of internal framing photo's - showing the structure of the home and how the framing stage looks in a bit of detail.
Alfesco

Front Door (Coming soon!)

Front room & windows

Garage

Laundry

Front of house

Bathroom


Sunday, 18 August 2013

Slab Down + Base Frame!

Master Bedroom (left) and front door (middle), garage on the cutoff (right)
Some real progress has happened now, with the slab down and a basic frame has been erected on the slab very shortly after it was poured.

It is great that we can now visualize and see the physical shape of the house form.The step-down for the garage doesn't look to high, which is good. It is however a step step-down for the alfresco, but that will be tiled and raised a bit in the future.

Panorama shot of the front of the house

We are now starting to look and visualize a bit more what we plan to do with the driveway (has to be done post build, but before we move in). We are hoping to have a wide driveway, that curves to the porch. Time and other constraints will tell how feasible this is.





Pre Slab

Following the delays of SE water, work had finally commenced on our house. A plumber had been in to place the piping in place and the foam/boards for the slab to set in
to had been put in place.

We hope that things can move forward at a fast pace - as it's a tight schedule to hopefully get in before the Christmas shutdown.
Pre-Slab